Nava Data Center Launch Project
Province: Tehran
Year of Execution: 2016
Implementation Stages Data Center
Needs assessment and initial design
-
Specify the number of users, servers, and network equipment
-
Determining the type of services (web, database, backup, firewall, camera, etc.)
-
Estimating power consumption and UPS capacity
-
Designing rack maps, cabling routes, and equipment layouts
Preparing space and physical infrastructure (Passive)
-
Choosing the right room (away from sunlight and electrical noise)
-
Implementing false floors and false ceilings for cable passage
-
Implementation of precision air conditioning (PAC) system
-
Installing a fire alarm and extinguishing system (such as FM200)
-
Implementing a separate electrical system with a special panel for the server room
-
Earthing (earthing well with resistance below 2 ohms)
-
Installing UPS and backup battery
Implementing a Passive Network
-
Ducting and piping according to the drawing
-
Network cabling (Cat6) and electricity
-
Installing patch panels, faceplates, and keystones
-
Installing a standing rack and a wall rack
-
Organizing cables with Cable Manager
-
Standard labeling of cables and ports
Installation of Active Equipment
-
Installing switches, routers, firewalls, and access points in a rack
-
Installing physical servers and storage
-
Connecting power and network to UPS and rack
-
Configuring VLAN, Routing, DHCP, NAT
-
Installing network monitoring software
Software deployment and virtualization
-
Installing server operating systems (Windows Server, Linux, ESXi)
-
Setting up Active Directory, DNS, DHCP
-
Installing and configuring a hypervisor for virtualization
-
Creating virtual machines (VMs) for services
-
Installing central antivirus, backup and monitoring software
-
Setting user access and Group Policy