Nava Data Center Launch Project

  1. Home
  2. »
  3. Nava Data Center Launch Project

Nava Data Center Launch Project

Province: Tehran
Year of Execution: 2016

Implementation Stages Data Center

Needs assessment and initial design
  • Specify the number of users, servers, and network equipment
  • Determining the type of services (web, database, backup, firewall, camera, etc.)
  • Estimating power consumption and UPS capacity
  • Designing rack maps, cabling routes, and equipment layouts
Preparing space and physical infrastructure (Passive)
  • Choosing the right room (away from sunlight and electrical noise)
  • Implementing false floors and false ceilings for cable passage
  • Implementation of precision air conditioning (PAC) system
  • Installing a fire alarm and extinguishing system (such as FM200)
  • Implementing a separate electrical system with a special panel for the server room
  • Earthing (earthing well with resistance below 2 ohms)
  • Installing UPS and backup battery
Implementing a Passive Network
  • Ducting and piping according to the drawing
  • Network cabling (Cat6) and electricity
  • Installing patch panels, faceplates, and keystones
  • Installing a standing rack and a wall rack
  • Organizing cables with Cable Manager
  • Standard labeling of cables and ports
Installation of Active Equipment
  • Installing switches, routers, firewalls, and access points in a rack
  • Installing physical servers and storage
  • Connecting power and network to UPS and rack
  • Configuring VLAN, Routing, DHCP, NAT
  • Installing network monitoring software
Software deployment and virtualization
  • Installing server operating systems (Windows Server, Linux, ESXi)
  • Setting up Active Directory, DNS, DHCP
  • Installing and configuring a hypervisor for virtualization
  • Creating virtual machines (VMs) for services
  • Installing central antivirus, backup and monitoring software
  • Setting user access and Group Policy